Sign up to receive a text message or email when new bids are added!
Bid Number: UT-001-20
Bid Title: Liberty Lime Feed Silo Procurement
Category: Construction
Status: Open

Description:
You are invited to bid on a procurement contract.  The Contract provides for the furnishing F.O.B. Project Site of one hydrated lime feed system including storage silo, hydrated lime feed equipment, and all appurtenances referred to as "Equipment and Materials" including manufacturer's Field Services for installation and unloading by others under separate Contract.  Project is at the following location:

Liberty Water Treatment Plant
1920 Clay Brooke Dr.
Liberty, MO  64068

Bids will be received by the Owner until 2pm, local time, July 9, 2020.  Bids received after this time will not be accepted.  Bids will be received at the following location:

City of Liberty City Hall
3rd Floor
101 E. Kansas
Liberty, MO  64068

Bids will be publicly opened and read aloud immediately after time stated above.


Publication Date/Time:
6/18/2020 7:00 AM
Publication Information:
City Website; Liberty Courier-Tribune Newspaper
Closing Date/Time:
Open Until Contracted
Submittal Information:
2:00pm, Local Time, Thursday, July 9, 2020
Bid Opening Information:
Public Opening
Contact Person:
Andy Noll
Utilities Director
anoll@libertymo.gov
816.439.4510

Amanda Caldwell-Jacques
Project Engineer
ascaldwelljacques@burnsmcd.com
816.627.6052

Plan & Spec Available:
Copies of the Bid Documents may be obtained for bidding purposes from Burns & McDonnell Engineering Company, Inc. (Engineer) in electronic (PDF) format only by contacting:

Amanda Caldwell-Jacques
Project Engineer
ascaldwelljacques@burnsmcd.com
816.627.6052

Business Hours:
8am-5pm M-F
Plan Holders List:
Amanda Caldwell-Jacques
Project Engineer
ascaldwelljacques@burnsmcd.com
816.627.6052
Qualifications:
Prequalification of lime system suppliers has already been completed and only equipment from those lime equipment suppliers listed in the Contract Documents will be opened. Bids received from Bidders who are not providing equipment from approved lime system suppliers will not be opened. Owner will evaluate Bidders in accordance with the Instructions to Bidders.
Special Requirements:
Bid security in the form of a Bid Bond in the amount not less than 5% of the total Bid price shall accompany each Bid in accordance with the Instructions to Bidders.

Completion time shall be as follows:

It is required that delivery of all Equipment and Materials necessary under this Contract be within 180 days following the date stated in Notice to Proceed.

Bids will be received on a Lump Sum with Alternates basis.

Bids received from Bidders who are not recorded by Engineer as having received the Bid Documents will not be opened.

Miscellaneous:
The Owner reserves the right to reject any or all Bids and to waive irregularities therein, and all Bidders must agree that such rejection shall be without liability on the part of the Owner for any damage or claim brought by any Bidder because of such rejections, nor shall the Bidders seek any recourse of any kind against the Owner because of such rejections. The filing of any Bid in response to this invitation shall constitute an agreement of the Bidder to these conditions.

Return To Main Bid Postings Page